A1 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Ceiling white wash completed
Toilet tiles laying in progress
Next We planned general floor tiles
A2 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Ceiling white wash completed
Toilet tiles laying in progress
Next We planned general floor tiles
A3 FLAT:
Shelf work in progress
Floor p... moreSTRUCTURE:
H/R and LMR column RCC planned
A1 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Ceiling white wash completed
Toilet tiles laying in progress
Next We planned general floor tiles
A2 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Ceiling white wash completed
Toilet tiles laying in progress
Next We planned general floor tiles
A3 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Bedroom alteration works in progress
Next We planned Tiles work
B1 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Ceiling white wash completed
1st coat wall putty work in progress
Toilet tiles laying in progress
Next We planned general floor tiles
B2 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Ceiling white wash completed
Toilet tiles laying in progress
Next We planned general floor tiles
B3 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Next We planned general floor tiles and Toilet tiles laying
B4 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Next We planned general floor tiles and Toilet tiles
C1 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Ceiling white wash completed
Toilet tiles laying in progress
Next We planned general floor tiles
C2 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Ceiling white wash completed
1st coat wall putty work completed
Next We planned general floor tiles and Toilet tiles laying
C3 FLAT:
Shelf work in progress
Floor plumbing works completed
Toilets brickjelly works completed
Toilet tiles laying in progress
Next We planned general floor tiles
Common:
parapet wall brickwork completed
Short column RCC work completed
Staircase and lobby area plastering work in progress
Stilt area plastering works in progress
West and South side Outer scaffolding works completed
Mesh fixing and Button marking completed
East side outer plastering completed
North side outer plastering completed
Ots area plastering work completed
West side outer plastering work in progress...!
We propose our next Apartment project in Alwarthirunagar, AGS Colony, Thilakar Street, very close to Suriya Mahal ! on a 30 feet road. Residential location.
Prime Location
Behind Suriya...
A1 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work completed
A2 FLAT:
kitchen PF rcc work completed.
plumbing wall chasing work completed
A3 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work completed.
B1 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing work completed.
B2 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing... moreSTRUCTURE:
H/R and LMR brick work in progress.
A1 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work completed
A2 FLAT:
kitchen PF rcc work completed.
plumbing wall chasing work completed
A3 FLAT:
kitchen PF rcc work completed
plumbing wall chasing work completed.
B1 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing work completed.
B2 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing work completed.
B3 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
plumbing wall chasing work completed.
B4 FLAT:
Inner wall plastering work completed.
kitchen pf rcc completed.
Plumbing wall chasing works in progress
C1 FLAT:
Inner wall plastering work completed.
Plumbing wall chasing works in progress
C2 FLAT:
Inner wall plastering work completed.
Plumbing wall chasing works in progress
C3 FLAT:
Inner wall plastering work completed.
Plumbing wall chasing works in progress
Common:
parapet wall and column RCC work in progress
Staircase and lobby area plastering works in progress
Stilt area plastering works in progress
Outer scaffolding works for plastering completed
Mesh fixing and Button marking in progress for outer plastering
Next we have planned for Outer plastering work
B1 FLAT:
Toilet wall and floor, General floor tiles work in progress - 98% completed
Kitchen pf granite work completed
Shelf work in progress
Inner wall putty and ceiling white wash completed.
B2 FLAT:
Inner wall 1st coat putty and ceiling white wash work completed
Kitchen pf granite work completed
Next we have planned tiles work.
Next we have planned shelf work
B3 FLAT:
Inner wall 1st coat putty work and ceiling white wash work completed
kitchen pf granite work completed
Shelf work... moreB1 FLAT:
Toilet wall and floor, General floor tiles work in progress - 98% completed
Kitchen pf granite work completed
Shelf work in progress
Inner wall putty and ceiling white wash completed.
B2 FLAT:
Inner wall 1st coat putty and ceiling white wash work completed
Kitchen pf granite work completed
Next we have planned tiles work.
Next we have planned shelf work
B3 FLAT:
Inner wall 1st coat putty work and ceiling white wash work completed
kitchen pf granite work completed
Shelf work in progress
next we have planned tiles work.
A1 FLAT
Shelf work completed.
tiles 98% work completed.
kitchen pf granite work completed
next we have planned wall putty work.
A2 FLAT.
toilet wall and floor tiles, General floor tiles in progress - 95% completed
kitchen pf granite work completed.
Shelf works in progress.
Next we have planned putty work.
A3 FLAT
Shelf work progress
kitchen pf granite work completed
next we have planned putty work.
next we have planned tiles work.
C1 FLAT:
inner wall putty work and ceiling white wash completed
kitchen pf granite work in progress.
Shelf work in progress
tiles work - 95% completed
C2 FLAT:
tiles 95% work completed.
inner wall putty and ceiling white wash work completed
kitchen pf granite work completed
COMMON:
Water tank base slab structural work in progress.
H/R, LMR - Plastering work in progress.
OUTER:
Outer plastering work completed.
Outer plumbing work completed.
Next we have planned parapet area plumbing works
🎊 Happy Birthday to Mrs.Gowri ! 🎂
May your special day be as inspiring and wonderful as you are. Your dedication and positive attitude make a great difference to the team.
Wishing you happiness, good health, success, and many more achievements in the coming year.